CityConnect Phase 3: Clay Pit Lane – Design Approval and Works Issue

26/05/2020 - CityConnect Phase 3: Clay Pit Lane – Design Approval and Works Issue

The Chief Officer, Highways & Transportation:
i) noted and approved the final layout of the Clay Pit Lane scheme as shown on the attached drawings (TM-00-470-01-01A/02/03);
ii) gave authority to issue the works to contractor and to construct the scheme as shown; and
iii) noted that the scheme, valued at £1.63M and comprising £1.46M works and £0.17M staff fees, is to be wholly funded from West Yorkshire Combined Authority’s CityConnect programme as previously approved by Executive Board and by WYCA.