The Director of Resources and Housing granted
approval to:
• Issue a Stage 1 Appointment Letter to appoint Willmott
Partnership Homes Ltd to design new build homes at Scott Hall Drive
(Chapeltown), Ramshead Approach (Seacroft), Barncroft Close
(Seacroft).
• Enter into an NEC3 Professional Service Contract (PSC) for
each scheme with Willmott Partnership Homes Ltd for the total sum
of £530,664.00 to develop design and cost proposals for the
scheme (including surveys).
• Delegate approval to Head of Council Housing Growth
Programme, as per the scheme of delegation, to approve any costs
incurred through the design stage for additional surveys or third
party consultancy costs.
• Delegate any minor extensions of the contract term and minor
increases to the design fees (up to £50,000) to the Head of
the Council Housing Growth Programme. The Head of the CHGP will
update the Director of Resources and Housing.