The Chief Officer (Highways & Transportation):

 

i)  approved the A660/A658 Dyneley Arms junction detailed design;

 

ii)  approved the conclusion of the necessary land acquisitions at an estimated cost of £25,000;

 

iii)  approved the injection of £1,521,408 funding into the capital programme from the West Yorkshire Transport Fund in addition to the previously injected funds of £765,000 for development and design fees;

 

iv)  gave authority to spend £2,286,408 funded from the West Yorkshire Transport Fund on receipt of Final Business Case Plus approval by the Combined Authority;

 

v)  approved the scheme delivery through the established Leeds City Council Term Contract for highway works at an estimated cost of £1,518,908 including enabling works, delivery and construction risk;

 

vi)  approved a variation to the scheme funding agreement with the Combined Authority to reflect the full final project costs on confirmation of the Final Business Case Plus approval by the Combined Authority; and

 

vii)  approved with reference to the powers contained in Section 66(4) of the Highways Act 1980, that the relevant lengths of footway shown on attached Drawing No 732827/LCC/HWT/DA/DR/CH/GA_01b that following the removal of the footways, the cycle track is constructed under the powers contained under the provisions of section 65(1) of the Highways Act 1980 for segregated or shared joint use by pedal cyclists and pedestrians.