The Director of Resources and Housing:
a) Approved the award of a contract to Cenergist Limited to
undertake the installation of ground source heat pumps for a
contract sum of £1.610m to two high rise blocks –
Westerly Croft and Westerly Rise; and
b) Noted that this follows a direct call off from the Procurement
for Housing (PFH) framework, and that it is proposed that these
works will be completed between December 2020 and March 2021,
and
c) Approved expenditure for an additional £100k to enable
delivery of the full project.