The Director of Communities, Housing and Environment:
a) Approved this scheme to replace existing heating and hot water systems in Queenswood Heights and Queenswood Court with a Ground Source Heat Pumps system and the award of a construction contract to Cenergist Limited to undertake the works for a contract sum of £1,531,545.19.
b) Authorised expenditure of £870k, using HRA funding from the 2022/23 capital programme to facilitate this. This will take the total Authority to Spend for this project to £1.62m as £750k of expenditure was authorised as part the 2021/22 HRA Capital Investment Programme.