Issue - decisions

Council House Growth Programme: award of the construction to deliver newbuild council homes at Tarnside Drive (including Mardale Crescent), Seacroft

01/04/2021 - Council House Growth Programme: award of the construction to deliver newbuild council homes at Tarnside Drive (including Mardale Crescent), Seacroft

The Director of Resources & Housing granted approval to enter into an NEC4 Engineering and Construction Contract (NEC4 ECC) Option A with Wates Construction Ltd for the construction of 41 new council homes at Tarnside Drive (including Mardale Crescent) for the sum of £9,191,098.48; enabling a contract start date for 6th April 2021, a site access date of 10th May 2021 and a completion date of 26th August 2022; and approval to spend.