Issue - decisions

Design Cost Report for Garforth Academy s106 works

04/10/2021 - Design Cost Report for Garforth Academy s106 works

Approve the injection of £123,429 of s106 contribution into the capital programme
Approve authority to spend and incur expenditure of £123,429 from capital scheme number 33177/BGE/GAR to deliver the works required to allow Garforth Academy to take an additional 25 places in Year 7 from September 2021.
Note that Children’s & Families Good Learning Places Board approved the use of s106 reference 11/02814 to fund the cost of capital works at Garforth Academy

Note that the officer responsible for implementation is the Head of Service Learning Systems in Children’s and Families Directorate.