The Chief Officer Asset Management and
Regeneration has given approval to the terms, as set out in
confidential Appendix 2, for:
a) Acquisition of third-party owned land to facilitate highway
improvement works required to Armley Gyratory.
b) An assignable call option in favour of the third-party over the
Council’s land in the event that the third-party obtains
planning permission for an alternative access to their site.
c) Entering into a Non-Disclosure Agreement with the third-party in
relation to a report summarising the ground conditions pertaining
to the acquisition land.
d) A Deed of Easement to be granted to the third-party to provide
them with full access rights between their two parcels of land
either side of the gyratory.
e) A Deed of Variation to an existing site compound lease the
Council has over the third-party’s land, which shall allow
for the acquisition land to be
surrendered from the demise, the introduction of working areas and
the
temporary installation of services.