The Chief Officer (Financial Services) was
requested to:
a) Inject £6,840,330 of additional roof tax envelope funding
for ELOR phase 3, Scholes Lane Junction and M1 Junction 46,
elements of the ELOR programme.
The Chief Officer (Highways and Transportation) was requested
to:
b) Approve the design and implementation of the Scholes Lane
scheme. Details are shown on drawing,
2021CAP01-LCC-HWT-XX-M2-CH-MaConsult-02, In Appendix A
c) Approve the implementation of the National Highways Jct 46
scheme, under licence via Sections 6 and 8 of the Highways Act,
1980.
d) Approve with reference to the powers contained in Section 66 (1)
of the Highways Act 1980 to construct pedestrian footway as shown
on drawing, 2021CAP01-LCC-HWT-XX-M2-CH-MaConsult-02
e) Approve with reference to the powers contained in Section 62 (1)
of the Highways Act 1980 to improve the highway as shown on drawing
2021CAP01-LCC-HWT-XX-M2-CH-MaConsult-02.
f) Authorise spend of £6,840,330 which is made up of
£2,826,000 for the ELOR phase 3 final settlement payment and
retention together with the sum of £1,292,160 for the Scholes
Lane junction scheme and £2,722,170 for the M1 junction 46
scheme.
g) Note that further reports will be brought forward at the
appropriate time to address the items in Paragraph 5.5.