Issue - decisions

Council Housing Growth Programme: Approval to enter into Pre-Construction Services Delivery Agreement to deliver the Extra Care Housing Scheme at Middlecross

07/05/2024 - Council Housing Growth Programme: Approval to enter into Pre-Construction Services Delivery Agreement to deliver the Extra Care Housing Scheme at Middlecross

The Chief Officer Asset Management & Regeneration has:-
a) Approved entering into an NEC4 Professional Services Contract (PSC) with Morgan Sindall Construction Limited (MSCL) to deliver services of Pre-construction, Design and other Professional Services to complete RIBA Stages 4 via the SCAPE framework for the Middlecross project, to the value of £370,513.
b) Approved a contingency budget to enable any surveys or other necessary costs to be met as detailed in Confidential Appendix B.