The Director of Children & Families agreed
to:
* Sanction the requirement to extend the 'Early Works Agreement'
with the LLEP for ICL to deliver a package of works to facilitate
the Learning Places expansion at Bramley Primary School. This will
take the form of an extension to the existing 'Early Works'
agreement between the authority and Leeds D&B One Ltd for the
sum of £577,000;
* approve the expenditure of £577,000 from capital scheme
number 32450/BRA/000 for the completion of a package of 'Early
Works' necessary to deliver the expansion of Bramley Primary School
for a September 2017 occupation. This is to be funded from the
£3.25m allocated for the full expansion of Bramley Primary as
part of the Learning Places Programme report approved at the
December 2016 Executive Board;
* note that a separate DCR will be submitted for the main works
once financial close has been achieved in May 2017;
* note that a previous 'Early Works' agreement has been approved at
a value of £249,000 which covered the April 2017 activity
schedule. The proposals detailed herein are in addition to this
figure and will cover the May 2017 activity schedule; and
* note that the officer responsible for implementation is the Head
of Learning Improvement.