The Director of Resources and Housing gave
approval of the award of the sprinklers framework agreement to
Armstrong Priestley, for the previously agreed sum of £3.76m,
now that the tender has been evaluated. The framework agreement
will commence June 2018 for a period of 2 years and 9 months to end
31 January 2021, with the option to extend for a further 1 x 12
month period, at the sole discretion of the Council; and approval
of the award of the first call-off contract from the framework for
sprinkler works to eight high rise. The estimated value of the
first call-off contract is £1.27m for works programmed to be
delivered from September 2018 until November 2020.