The Director of Children and Families agreed
to:
• Approve the request to award the contract for the sum of
£426,595.54 to Kier Construction Northern for the purchase
and installation of temporary accommodation.
• Authorise the signature of all contractual documentation
with Kier Construction Northern in relation to the tender
acceptance.
• Note the programme dates identified in section 4.0 of this
report, in relation to the implementation of this decision.
• Note that the whole scheme will be completed in June
2019.