To provide authority to enter into an ERDF grant agreement for FTF to install renewable energy generation and storage systems and insulate 250 houses owned by Leeds City Council.
To inject ERDF grant funding into the Capital Programme with match funding provided from the non traditional and hard to treat budget, within the approved Housing Revenue Account Capital Programme;
To provide authority to spend to deliver the entire FTF programme.
To provide authority to award a contract to deliver this work to a competitively selected contractor.
Decision type: Key
Reason Key: Financial Impact>£500K;
Decision status:
Wards affected: Bramley and Stanningley; Hunslet and Riverside; Killingbeck and Seacroft; Middleton Park;
Notice of proposed decision first published: 10/10/2019
Decision due: Not before 8th Nov 2019 by Director of Resources
Lead director: Director of Resources
Department: Resources and Housing
Contact: Sandy Rutherford, Programme Manager Email: sandy.rutherford@leeds.gov.uk.
Consultation process
Housing Leeds and Finance have been involved in the project since its inception in September 2017. Ward members in all areas will be briefed on the project and will be kept informed as decisions are made on grant and contract award. The Executive Members for Communities and Climate Change, Transport and Sustainable Development will be separately consulted.
Consultees
Housing Leeds Capital Programme
Chief Officer Property and Contracts
Finance
Environment Programme Board
Executive Member for Communities
Executive Member for Climate Change, Transport and Sustainable Development