Issue details

Connecting West Leeds (CWL) Phase 2 Schemes - Design and Construction

Authority to spend circa £12m+ on the Design and Construction of seven Phase 2 schemes funded by The Department for Transport Levelling Up Fund and supplemented by City Regional Sustainable Transport Settlement (CRSTS) and S106 funding.

 

Connecting West Leeds (CWL) Phase 2 Schemes consisting of:

- Section 4: Calverley Lane Bridge

- Section 5: Dawsons Corner to Rodley Footway and Cycleway Link

- Section 6: Rodley Roundabout Technology Improvements

- Section 7: Calverley La North & Calverley Bridge road safety measures

- Section 8: Footway and Cycle Ramp to Canal

- Section 9: Landscape Mitigation

- Section 10: Average Speed Camera Enforcement

 

Decision type: Key Decision

Reason Key: Financial Impact>£500K;

Decision status:

Wards affected: Bramley and Stanningley; Calverley and Farsley; Horsforth; Pudsey;

Notice of proposed decision first published: 03/02/2023

Decision due: Not before 6th Mar 2023 by Director of City Development

Lead director: Director of City Development

Department: City Development

Contact: Mohammed Mahmood, Senior Transport Planner 0113 378 7524 Email: mohammed.mahmood@leeds.gov.uk.

Consultation process

CWL Phase 2 public consultation was hosted on the Leeds City Council Connecting West Leeds Commonplace webpage and ran from 12 July 2022 to 11 September 2022, https://connectingwestleedstwo.commonplace.is/

, this also included five face to face drop in events in Pudsey, Rodley, Farsley, Calverley and Horsforth.

Consultees

The following key stakeholders have also been consulted:

  Executive Board Member for Infrastructure and Climate;

  Local Ward Members;

  Internal LCC Officers;

  Members of Public (online and drop in event); and

  Cycle Sub-Group.

Decisions