LBS is currently mobilising a number of new materials providers. This is a complex project that requires a significant amount of ICT interfacing between the Council’s Total Connect system and the new providers’ systems - in addition to other mobilisation matters such as acquiring new premises.
The service is therefore seeking approval to vary the contract with the existing provider, Wolseley UK Limited for 3 months. This will ensure that LBS and the new suppliers have sufficient time to mobilise and ensure a smooth handover.
The contract Wolseley UK Ltd will be varied, and extended untill 30th June 2023.
Decision type: Key
Reason Key: Financial Impact>£500K;
Decision status:
Wards affected: (All Wards);
Notice of proposed decision first published: 03/02/2023
Decision due: Not before 6th Mar 2023 by Director of Resources
Lead director: Director of Resources
Department: Resources
Contact: Craig Simpson, Head of Leeds Building Services 01133785416 Email: Craig.Simpson@leeds.gov.uk.