Issue details

Decisions taken in relation to connecting additional customers to Leeds PIPES District Heating Network

-  Approving the council entering into Connection and Supply Agreements with a number of prospective customers for Leeds PIPES

-  Approving the awarding of contract/contracts to the project’s Principal Contractor for detailed design at a number of sites to facilitate connections to Leeds PIPES, utilising standard council T&Cs

-  Approving the awarding of contract/contacts to the project’s Principal Contractor for works to connect customers to Leeds PIPES, utilising an NEC3 contract

Potential customers to be detailed in the accompanying Key Decision report.

Decision type: Key

Reason Key: Financial Impact>£500K;

Decision status:

Wards affected: (All Wards);

Notice of proposed decision first published: 03/03/2023

Decision due: Not before 3rd Apr 2023 by Director of Communities, Housing & Environment

Lead director: Director of Communities, Housing & Environment

Department: Resources

Contact: Joe Callin, Senior Project Officer Email: joseph.callin@leeds.gov.uk.

Consultation process

The Director for Resources, the Director for Communities, Housing and Environment, and the Executive Member for Infrastructure and Climate will continue to be consulted in the lead up the decision being taken, and will be reported to regularly on progress of the implementation of the decisions.

Consultees

Director for Communities, Housing and Environment

Director for Resources

Executive Member for Infrastructure and Climate

Procurement and Commercial Services

Governance

Highways and Transportation

Decisions