- Approving the council entering into Connection and Supply Agreements with a number of prospective customers for Leeds PIPES
- Approving the awarding of contract/contracts to the project’s Principal Contractor for detailed design at a number of sites to facilitate connections to Leeds PIPES, utilising standard council T&Cs
- Approving the awarding of contract/contacts to the project’s Principal Contractor for works to connect customers to Leeds PIPES, utilising an NEC3 contract
Potential customers to be detailed in the accompanying Key Decision report.
Decision type: Key
Reason Key: Financial Impact>£500K;
Decision status:
Wards affected: (All Wards);
Notice of proposed decision first published: 03/03/2023
Decision due: Not before 3rd Apr 2023 by Director of Communities, Housing & Environment
Lead director: Director of Communities, Housing & Environment
Department: Resources
Contact: Joe Callin, Senior Project Officer Email: joseph.callin@leeds.gov.uk.
Consultation process
The Director for Resources, the Director for Communities, Housing and Environment, and the Executive Member for Infrastructure and Climate will continue to be consulted in the lead up the decision being taken, and will be reported to regularly on progress of the implementation of the decisions.
Consultees
Director for Communities, Housing and Environment
Director for Resources
Executive Member for Infrastructure and Climate
Procurement and Commercial Services
Governance
Highways and Transportation