The Chief Officer for Highways & Transportation to give progress Sheepscar Beck Flood Alleviation scheme through to completion of construction.
Decision type: Key Decision
Reason Key: Financial Impact>£500K;
Decision status:
Wards affected: Burmantofts and Richmond Hill; Little London and Woodhouse;
Notice of proposed decision first published: 07/09/2023
Decision due: Not before 6th Oct 2023 by Director of City Development
Lead director: Director of City Development
Department: City Development
Contact: Matthew Sherwood, Senior Engineer 0113 378 7418 Email: matthew.sherwood@leeds.gov.uk.
Consultation process
Executive Member and Ward Members were provided with a scheme update via email on 8th August 2023.
Residents and businesses in the area of the scheme have been contacted via a letter drop in August 2023 directing them towards our Common Place portal providing further information on the proposed works & seeking feedback on our proposals.
Consultees
Ward Members, LCC Internal Stakeholders, Environment Agency, West Yorkshire Combined Authority, local residents and businesses.