Reference: D56755
Decision Maker: Director of Communities, Housing & Environment
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The Director of Communities, Housing and
Environment has approved the award of a construction contract for
the installation of a communal Ground Source Heat Pump system to
provide heating and hot water and a fire suppression sprinkler
system, to Clayton Court and Grange for the sum of
£3,294,317.93, to Cenergist Limited.
The contract will start on the 4th September 2023 and end on the
31st March 2024.
Wards Affected: Kirkstall;
Contact: Ricahrd Stokes, Capital Programme Project Manager 0113 378 5977 Email: richard.stokes@leeds.gov.uk.
Publication date: 06/09/2023