The Head of Learning Systems agreed to:
• Incur costs of £228,949.13 associated with the Pre-Construction Services Agreement from capital scheme number 33471/LCA/000.
• Incur costs of £78,789 associated with RIBA stage 4 fees.
• Note the programme dates identified at point 9 of this report require a decision at the earliest opportunity to enable detailed design work to continue and for the project to remain on programme.