Details of officer decisions relating to planning applications.
Decision Maker: Director of City Development
Decision published: 05/02/2021
Effective from:
Decision:
The Chief Officer of Asset Management and
Regeneration is requested to approve the appointment of Cushman and
Wakefield (UK) LLP to undertake a full professional agency service
in order to appropriately market the subject assets within the
specialist investment sector and provide professional support
throughout . The cost will be based on a percentage of the achieved
sale price.
Wards affected: Temple Newsam;
Lead officer: Mary Stockton
Decision Maker: Director of City Development
Decision published: 05/02/2021
Effective from:
Decision:
The Chief Officer Asset Management &
Regeneration has given approval to the procurement of external
rating advice and rating appeal work in relation to the 2010 and
2017 Rating Lists on terms provisionally agreed and covered by the
Crown Commercial Services framework.
Wards affected: (All Wards);
Lead officer: Darren Wilding
Decision Maker: Director of Children and Families
Decision published: 05/02/2021
Effective from:
Decision:
The Director of Children & Families agreed
the recommendation of a report relating to the placement of a
child/young person. The individual costs of the place are
£401,500.00.
It is considered in the public interest that information contained
in the report is exempt from publication as it relates to a
vulnerable child or young person of the City and the actions being
taken to enable that person to live in a safe environment.
Wards affected: Various;
Lead officer: Ben Finley
Decision Maker: Director of Children and Families
Decision published: 05/02/2021
Effective from:
Decision:
The Director of Children & Families agreed
the recommendation of a report relating to the placement of a
child/young person. The individual costs of the place are
£511,000.00.
It is considered in the public interest that information contained
in the report is exempt from publication as it relates to a
vulnerable child or young person of the City and the actions being
taken to enable that person to live in a safe environment.
Wards affected: Various;
Lead officer: Ruth Terry
Decision Maker: Director of Children and Families
Decision published: 05/02/2021
Effective from:
Decision:
The Director of Children & Families agreed
the recommendation of a report relating to the placement of a
child/young person. The individual costs of the place are
£321,565.00.
It is considered in the public interest that information contained
in the report is exempt from publication as it relates to a
vulnerable child or young person of the City and the actions being
taken to enable that person to live in a safe environment.
Wards affected: Various;
Lead officer: Ruth Terry
Decision Maker: Director of Children and Families
Decision published: 05/02/2021
Effective from:
Decision:
The Director of Children & Families agreed
the recommendation of a report relating to the placement of a
child/young person. The individual costs of the place are
£354,571.43.
It is considered in the public interest that information contained
in the report is exempt from publication as it relates to a
vulnerable child or young person of the City and the actions being
taken to enable that person to live in a safe environment.
Wards affected: Various;
Lead officer: Ruth Terry
Decision Maker: Director of City Development
Decision published: 05/02/2021
Effective from:
Decision:
The Chief Officer Asset Management and
Regeneration has approved the purchase of a property on the terms
detailed in the confidential appendix for Resources and Housing to
return to Council stock.
Wards affected: Gipton and Harehills;
Lead officer: Diane McPhee
To seek approval from the Director of Resources and Housing on the reallocation of unspent Clean Air Funding (£5.57m), specifically, to note the extension of existing grant packages and the creation of a new financial support scheme (free licensing) for the Taxi and Private Hire sector. This approval is sought to ensure compliance with the Council’s constitution with regard to repurposing these Government allocated funds.
Decision Maker: Director of Resources
Decision published: 05/02/2021
Effective from: 23/02/2021
Decision:
The Director of Resources and Housing:
· Noted that £0.627m is retained for miscellaneous administration costs (ongoing communications, operational management and associated costs of discharging funds and managing risk).
· Noted that any unspent funding from the £5.57m is to be returned to Central Government.
Wards affected: (All Wards);
Lead officer: Claire Dalton Nobbs
Approval needed to undertake procurement of multitrade contractors to support LBS with delivery of responsive repairs, voids and maintenance to domestic properties.
The contract will be for an initial term of 4 years with the option to extend for 4 x 12 month periods. We will be looking to appoint a maximum of 6 contractors within 6 lots.
Decision Maker: Director of Resources
Decision published: 05/02/2021
Effective from: 23/02/2021
Decision:
The Director of Resources & Housing approved an above threshold restricted procedure to establish a contract of up to 7 contractors, valued at £3 million per annum, starting on 1st July 2021 for a term of 4 years, with the option to extend for 4 x 12 months. The maximum value of the contract if all extensions are used is £24,000,000.
Wards affected: Various;
Lead officer: Craig Simpson
Decision Maker: Director of City Development
Decision published: 04/02/2021
Effective from:
Decision:
The Chief Officer (Highways and
Transportation):
a) noted the detail of the highway works described in outline in
section 3 of this report and shown on plan AMA-40001-D-001 Rev I
attached at Appendix 3 of this report;
b) gave authority to negotiate the terms of and enter into an
agreement with the developer under the provisions of Section 278 of
the Highways Act 1980; whereby the works associated with the
development are carried out by the developer and overseen by the
Council.
c) approved the adoption of new highway construction on land
outlined in blue on plan AMA-40001-D-001 Rev I attached at Appendix
3 of this report so that it can be added to the Council’s
maintenance regime;
d) gave authority to advertise a notice under the provisions of
Section 23 of the Road Traffic Regulation Act 1984 and Section 90c
of the Highways Act 1980 in order to inform the public of the new
zebra crossing position on Chartists Way;
e) authorised the City Solicitor to advertise notices under the
provisions of Section 23 of the Road Traffic Regulation Act 1984
and Section 90c of the Highways Act 1980 and to advertise a Draft
Traffic Regulation Order to introduce No Waiting At Any Time
restrictions along Chartists Way as indicated on plan
AMA-40001-D-005 Rev F attached at Appendix 4 of this report; and if
no valid objections are received, to make, seal and implement the
Orders as advertised; and
f) gave authority to incur expenditure of £10,000 TRO costs
and £6,000 staff checking and inspection costs, all to be
fully rechargeable to the developer through the Section 278
agreement.
Wards affected: Morley South;
Lead officer: Michael Norcliffe
Decision Maker: Director of City Development
Decision published: 03/02/2021
Effective from:
Decision:
The Chief Planning Officer has re-designated
the Kirkstall Neighbourhood Forum for the Kirkstall Neighbourhood
Area.
Wards affected: Kirkstall;
Lead officer: Emma Lewis
Decision Maker: Director of City Development
Decision published: 02/02/2021
Effective from:
Decision:
The Chief Officer, Highways &
Transportation;
i) Noted and approved the final layout of the Cottingley Hall
Estate – Public Transport Infrastructure Improvement scheme
as shown on the attached Drawing No TM/25/1/321/GA-2A;
ii) Gave authority to issue the works to the term contractor and to
construct the scheme as shown.
iii) Noted the required expenditure of £647,000, comprising
£510,000 works costs, £50,000 Statutory Undertakers
diversionary costs, £86,000 staff fees and £1,000 legal
fees, all being funded from the Connecting Leeds programme as
previously approved by Executive Board and the Combined
Authority’s Project Assurance Team.
iv) Noted that the scheme, valued at £647,000, is to be
wholly funded from West Yorkshire Combined Authority’s
Connecting Leeds programme as previously approved by Executive
Board.
v) Gave authority to advertise and introduce a Traffic Regulation
and Movement Order to introduce waiting restrictions and bus lane
respectively as shown on the attached drawing no. TM/25/1/321/GA-2A
and if no valid objections are received, to make, seal and
implement the Traffic Regulation and Movement Orders, as
advertised; and
vi) Authorised the City Solicitor to advertise draft Traffic
Regulation and Movement Orders and if no valid objections are
received, to make, seal and implement the Orders and pedestrian
crossings as advertised
Wards affected: Beeston and Holbeck;
Lead officer: Nick Borras
Decision Maker: Director of City Development
Decision published: 02/02/2021
Effective from:
Decision:
The Chief Officer, Highways &
Transportation;
a) Noted and approved the final layout of the Bramley Bus
Interchange scheme as shown on the attached Drawing Nos
TM/06/368/GEN/02 & TM/06/368/TRO/01;
b) Gave authority to issue the works to the term contractor and to
construct the scheme as shown.
c) Noted the required expenditure of £459,000, comprising
£270,000 works costs, £125,000 Statutory Undertakers
diversionary costs and £64,000 staff fees, all being funded
from West Yorkshire Combined Authority’s Connecting Leeds
programme ( previously approved );
d) Noted that the scheme, valued at £459,000, is to be wholly
funded from West Yorkshire Combined Authority’s Connecting
Leeds programme as previously approved by Executive Board.
e) Gave authority to advertise and introduce a Traffic Regulation
and Movement Order to introduce waiting restrictions and bus lane
respectively as shown on the attached drawing no. TM/06/369/TRO/01
and to advertise a notice under the provision of Section 23 of the
Highways Act 1980 associated with provision of pedestrian crossings
and if no valid objections are received, to make, seal and
implement the Traffic Regulation and Movement Orders and implement
the pedestrian crossings, as advertised.
f) Authorised the City Solicitor to advertise draft Traffic
Regulation and Movement Orders and to advertise a notice under the
provision of Section 23 of the Highways Act 1980 associated with
provision of a pedestrian crossing and if no valid objections are
received, to make, seal and implement the Orders and pedestrian
crossings as advertised
Wards affected: Bramley and Stanningley;
Lead officer: Chris Procter
Decision Maker: Director of Resources
Decision published: 02/02/2021
Effective from:
Decision:
At the ELI panel held on (13.01.2021)
individual decisions were made in relation to each reaffirmed
expression of interest for both the Council’s ELI scheme and
flexible retirement requests.
In consultation with the Chief Financial Services Officer and each
individual Director, the Chief Officer Human Resources approved the
following:
(2) people to leave under the Council’s ELI Scheme
(4) colleagues to take flexible retirement
The cumulative savings for each individual decision associated with
the above is £415,250 over the next 5 years. Actual final
savings may be impacted upon by other associated costs (such as
reconfiguration costs ) and the outcome will be determined in due
course.
Lead officer: Jessica Dolphin
Decision Maker: Director of Resources
Decision published: 02/02/2021
Effective from:
Decision:
At the ELI panel held on (16.12.2020)
individual decisions were made in relation to each reaffirmed
expression of interest for both the Council’s ELI scheme and
flexible retirement requests.
In consultation with the Chief Financial Services Officer and each
individual Director, the Chief Officer Human Resources approved the
following:
(54) people to leave under the Council’s ELI Scheme
(13) colleagues to take flexible retirement
The cumulative savings for each individual decision associated with
the above is £7,648,718 over the next 5 years. Actual final
savings may be impacted upon by other associated costs (such as
reconfiguration costs ) and the outcome will be determined in due
course.
Lead officer: Jessica Dolphin
Decision Maker: Director of Resources
Decision published: 02/02/2021
Effective from:
Decision:
At the ELI panel held on (04.12.2020)
individual decisions were made in relation to each reaffirmed
expression of interest for both the Council’s ELI scheme and
flexible retirement requests.
In consultation with the Chief Financial Services Officer and each
individual Director, the Chief Officer Human Resources approved the
following:
(46) people to leave under the Council’s ELI Scheme
(8) colleagues to take flexible retirement
The cumulative savings for each individual decision associated with
the above is £6,141,068 over the next 5 years. actual final
savings may be impacted upon by other associated costs (such as
reconfiguration costs ) and the outcome will be determined in due
course’
Lead officer: Jessica Dolphin
Decision Maker: Director of Resources
Decision published: 02/02/2021
Effective from:
Decision:
At the ELI panel held on (06/11/2020)
individual decisions were made in relation to each reaffirmed
expression of interest for both the Council’s ELI scheme and
flexible retirement requests.
In consultation with the Chief Financial Services Officer and each
individual Director, the Chief Officer Human Resources approved the
following:
(122) people to leave under the Council’s ELI Scheme
(13) colleagues to take flexible retirement
The cumulative savings for each individual decision associated with
the above is £13,219,944 over the next 5 years. Actual final
savings may be impacted upon by other associated costs (such as
reconfiguration costs ) and the outcome will be determined in due
course.
Lead officer: Jessica Dolphin
Decision Maker: Director of Resources
Decision published: 02/02/2021
Effective from:
Decision:
At the ELI panel held on (11.11.2020)
individual decisions were made in relation to each reaffirmed
expression of interest for both the Council’s ELI scheme and
flexible retirement requests.
In consultation with the Chief Financial Services Officer and each
individual Director, the Chief Officer Human Resources approved the
following:
(206) people to leave under the Council’s ELI Scheme
(27) colleagues to take flexible retirement
The cumulative savings for each individual decision associated with
the above is £20,785,773 over the next 5 years. Actual final
savings may be impacted upon by other associated costs (such as
reconfiguration costs ) and the outcome will be determined in due
course.
Lead officer: Jessica Dolphin
Decision Maker: Director of Resources
Decision published: 02/02/2021
Effective from:
Decision:
At the ELI panel held on (27/10/2020)
individual decisions were made in relation to each reaffirmed
expression of interest for both the Council’s ELI scheme and
flexible retirement requests.
In consultation with the Chief Financial Services Officer and each
individual Director, the Chief Officer Human Resources approved the
following:
(171) people to leave under the Council’s ELI Scheme
(20) colleagues to take flexible retirement
The cumulative savings for each individual decision associated with
the above is £18,450,062 over the next 5 years. actual final
savings may be impacted upon by other associated costs (such as
reconfiguration costs ) and the outcome will be determined in due
course’
Lead officer: Jessica Dolphin
Decision Maker: Director of Resources
Decision published: 02/02/2021
Effective from:
Decision:
At the ELI panel held on (14/10/2020)
individual decisions were made in relation to each reaffirmed
expression of interest for both the Council’s ELI scheme and
flexible retirement requests.
In consultation with the Chief Financial Services Officer and each
individual Director, the Chief Officer Human Resources approved the
following:
(30) people to leave under the Council’s ELI Scheme
(5) colleagues to take flexible retirement
The cumulative savings for each individual decision associated with
the above is £5,446,256 over the next 5 years. Actual final
savings may be impacted upon by other associated costs (such as
reconfiguration costs ) and the outcome will be determined in due
course.
Lead officer: Jessica Dolphin
Decision Maker: Director of Resources
Decision published: 02/02/2021
Effective from:
Decision:
At the ELI panel held on (06/10/2020)
individual decisions were made in relation to each reaffirmed
expression of interest for both the Council’s ELI scheme and
flexible retirement requests.
In consultation with the Chief Financial Services Officer and each
individual Director, the Chief Officer Human Resources approved the
following:
(181) people to leave under the Council’s ELI Scheme
(9) colleagues to take flexible retirement
The cumulative savings for each individual decision associated with
the above is £21,408,395 over the next 5 years. Actual final
savings may be impacted upon by other associated costs (such as
reconfiguration costs) and the outcome will be determined in due
course.
Lead officer: Jessica Dolphin
Decision Maker: Director of Resources
Decision published: 02/02/2021
Effective from:
Decision:
At the ELI panel held on (28/09/2020)
individual decisions were made in relation to each reaffirmed
expression of interest for both the Council’s ELI scheme and
flexible retirement requests.
In consultation with the Chief Financial Services Officer and each
individual Director, the Chief Officer Human Resources approved the
following:
(17) people to leave under the Council’s ELI Scheme
(0) colleagues to take flexible retirement
The cumulative savings for each individual decision associated with
the above is £2,032,722 over the next 5 years.
Wards affected: (All Wards);
Lead officer: Jessica Dolphin
Decision Maker: Director of Resources
Decision published: 02/02/2021
Effective from:
Decision:
The Chief Officer Sustainable Energy and Air
Quality has approved the waiver of CPR 8.1 and 8.2 to award a
contract to Sweco UK Ltd to carry out feasibility studies for
potential Phase 3 extensions of the District Heating Network to the
Southbank. The studies are funded through HNDU and Energy
Accelerator grant funding, which restrict the councils ability to
carry out a competitive procurement.
Lead officer: Chris O'Brien
The council is responsible for deciding on a local schools funding formula for 2021/22, in order to distribute the Schools Block funding of the Dedicated Schools Grant (DSG) to all maintained schools and academies for their pre-16 pupils.
Decision Maker: Director of Children and Families
Decision published: 02/02/2021
Effective from: 18/02/2021
Decision:
In the absence of the Director of Children and Families, the Chief Officer, Resources and Strategy approved the schools funding formula for 2021/22.
Wards affected: (All Wards);
Lead officer: Lucie McAulay
Decision Maker: Leader of Council
Decision published: 01/02/2021
Effective from:
Decision:
To assign to Councillor Fiona Venner, in
addition to existing Executive Member responsibilities for Children
and Families, the Executive Member Portfolio for Health, Wellbeing
and Adults.
The amended Executive Arrangements, will be reflected in amended
documents at Part 3 Section 3a, 3b(a) and 3b(b) of the
Constitution.
Lead officer: Leader of Council
Decision Maker: Director of Communities, Housing & Environment
Decision published: 29/01/2021
Effective from:
Decision:
The Chief Officer Elections and Regulatory
approved the decision to issue taxi and private hire vehicle
licences for an additional period of 2 months without a vehicle
inspection, to allow the inspection to take place, under reduced
Covid staffing arrangements.
Wards affected: (All Wards);
Lead officer: Andrew White
Decision Maker: Director of Resources
Decision published: 29/01/2021
Effective from: 29/01/2021
Decision:
The Director of Resources & Housing
approved the deletion of two posts (Head of Communications and
Marketing post – temporarily - and Emergency Planning
Manager), the arrangements set out below for covering the posts,
and that the service retains a very small amount of funding
required to support the proposed arrangements to ensure business
continuity. This includes (with JDs and manager checklists in
relevant annexes):
- a regrade for the principal officer in CXs unit, backdated to the
relevant ELI date (annex 1);
- continued temporary honoraria for the shared cover for
communications and marketing functions, backdated to the relevant
ELI date (annex 2);
- two temporary honoraria posts in CXs office to provide management
support for functions to make the organisational design principles
work (annex 3 & 4);
- also, that the post/postholder of Head of Business Planning and
Risk transfers to Finance, but that the savings are attributed to
Strategy and Improvement as agreed with the CO Finance.
Lead officer: Mariana Pexton
Decision Maker: Director of Resources
Decision published: 29/01/2021
Effective from: 29/01/2021
Decision:
The Chief Officer Sustainable Energy
& Air Quality:
a) Approved the appointment of Ove Arup & Partners Ltd to
provide NEC3 supervisor and project management support for the
phase 2 extension of the district heating network, with a contract
value of £132k.
Wards affected: Little London and Woodhouse;
Lead officer: Chris O'Brien
Decision Maker: Director of Communities, Housing & Environment
Decision published: 28/01/2021
Effective from:
Decision:
The Chief Officer, Elections & Regulatory
approved the making of the draft Order attached as Appendix 1, to
appoint the Ledston residents named in the Order as interim Parish
Councillors until an election has been held to fill the vacancies
on 6 May 2021.
Wards affected: Kippax and Methley;
Lead officer: Susanna Benton
Decision Maker: Director of Adults and Health
Decision published: 28/01/2021
Effective from:
Decision:
The Chief Officer, Resources and Strategy of
Adults and Health, approved the award of the Contract for
Independent Persons and Independent Investigation Services to RRC
(RRConsultancy) Limited commencing on 1st February 2021 and will
expire on 31st January 2026.
There will be an option to extend for a further period of 12
months.
Wards affected: (All Wards);
Lead officer: Judith Kasolo
Decision Maker: Director of Public Health
Decision published: 28/01/2021
Effective from:
Decision:
Leeds City Council has received £10.4m,
from the Government, to support the public health response to the
COVID-19 pandemic. The funding is a one-off contribution, for the
2020-21 financial year, and is non-recurrent.
The funding is to support proactive and preventative evidence based
measures, in the fight against the pandemic. As part of this
allocation, a budget has been identified for measures that support
immediate support for Children and Families activity which will
support public health interventions as part of the Public Health
response to COVID-19:-
Due to the global Public Health emergency COVID-19 pandemic this
report provides detail of programmes to to temporarily increase the
capacity of the Early Years Learning Improvement Team,
Children’s Residential Care teams within the Children and
Families Directorate, 0-19 service within Leeds Community Health
Care Trust (LCH), and Leeds City College to support the prevention,
notification and management of COVID-19 in Leeds. Private,
Voluntary and Independent Nurseries, 0-19 services and the FE
sector, due to the nature of this requirement the duration will be
from December 2020 to June 2021.
To purchase digital devices and the provision of initiatives which
will increase contact with harder to reach families to support them
to prevent the spread of COVID-19 including by sharing prevention
and outbreak management messages , increasing adhering to
self-isolation and testing guidance.
These programmes will be funded from the Test and Trace ring-fenced
grant and total £348,691
Internal and External Staffing - £168,766
• COVID-19 Champion Role Private, Voluntary Independent (PVI)
Nursery sector (LCC) - £20,385
COVID-19 Champion roles 2 x 0.50wte SO2 post seconded from within
early years learning improvement team at a cost of £20,385
(December 2020 to May 2021) to support and manage the process to
enable PVI settings to effectively notify, prevent and manage
COVID-19 incidents and outbreaks.
• COVID-19 Coordinator roles Children Residential Care
Settings (LCC) - £72,129
Registered Home Manager 8 x 0.20wte P05 to update and amend
individual homes staffing Rotas for each community home, submit
CF50 notices, liaise with advisors (H&S, Occ. Health, PHE,
Ofsted Etc.) in response to managing COVID-19 related pressure. -
£44,919 (January 2021 to June 2021)
Project Support Officer 1 x 0.80wte SO1 – SCP 25 to manage
the reports related staffing levels across the community homes,
organising & running ongoing recruitment for staffing and
causals for critical cover, pre. Planning for induction of new
staff - £15,360 (January 2021 to June 2021)
Administration assistant 1 x 0.60wte (B1 SCP 5) at Adel Beck Secure
Children’s homes coordinated staffing resource to redeploy to
homes, provide returns to regulators required by the secure estate
- £7,393 (January 2021 to June 2021)
Youth worker senior support 1 x 0.10wte 52.5%DIR to undertake
weekly check ins to discuss and respond to residential pressures
related to COVID19 - £4,457. (January 2021 to June
2021)
All of the above are existing posts that have been redesigned to
enable the service to respond to COVID.
COVID-19 Champion Leeds Community Healthcare (LCH) 0-19 services -
£19,272
Family Health Worker 1 x wte NHS grade 4 - £19,272 (January
2021 to June 2021) seconded from the existing service to work as
part of the clinical triage team to provide advice and support to
children, young people, and families who contact the service with a
specific COVID-19 related enquiry or need or are a contact to
minimise harm and enable them to follow guidance to self-isolate as
required.
COVID-19 Champion and administrator Further Education settings
(Hosted by Leeds City College) - £56,980
COVID-19 Champion 1 x 1.0wte SO1 and 1 x 1.0wte LS4 (January 2021
to June 2021) to support and manage the process to enable Further
Education settings to effectively notify, prevent and manage
COVID-19 incidents and outbreaks - £56,980.
These are existing posts and funding will be used to enable them to
have dedicated time to fulfil this work
COVID-19 sport sessions for young people - £60,000
A grant of £60,000 provided to Street Games to enable 15
local third sector groups that make up the Youth COVID-19 response
network to deliver further COVID-19 projects for Young People. A
new Family door steps sports sessions to create a positive platform
to share COVID-19 messages. £45,000 will be provided to fund
grants to each third sector group and £15,000 will be
provided to Street Games to for overheads, coordination, monitoring
and evaluation of the projects.
Digital Devices, training and equipment - £119,925
This decision details the authority to procure and fund the
purchase of digital devices and a range of activities to increase
understanding of and adherence to testing, contact tracing and
self-isolation advice among children, young people, families and
parents to be, targeting those less likely to adhere to central
guidance and at increased risk of poorer outcomes as a result of
COVID-19. The funding will be used to increase family’s
virtual and face to face access to services they already have an
established and trusting relationship with. Each service will
provide the opportunity for families to discuss COVID-19 and will
offer tailored support to enable families to minimise the spread of
the virus. This will be delivered in partnership with DIS who will
purchase the devices on behalf of the organisations and 100%
Digital who support maintenance and management of the devices for
loan including longer term. This report provides authority for DIS
to procure the required digital devises for the purposes detailed
in this report
The plan consists of the following, all costs are approximate at
this stage:-
Homestart – £10,402
Purchase of 12 x iPads and 1 x laptop and £200 phone top up
data purchased via DIS (a division of the Council)
• 12 x iPads = £7,342
• 1 x laptop = £600 + £240 software =
£840
• 1 x phone top up = £200
A grant provided to Homestart to provide 2 hours per week of
coordinator time for 3 months provided by Homestart practitioners
and families to increase access to virtual young parents -
£2,020
Children’s Centres – £37,765
Purchase of 40 x Ipads and 30 x smart phones, including data
purchased via DIS linked to 100% digital to enable a minimum of 200
additional vulnerable families to access virtual support from
Children Centres, purchased by DIS (a division of the
Council)
• 30 x smart phones = £10,500
• rental charge = £2,790
• 40 x iPads = £24,475
Women’s Health Matters- £19,960
40 x devices including set up, training, IT support and delivery to
households for use by vulnerable families working with
Women’s Health Matters purchased by DIS (a division of the
Council)
Purchase of
• 40 x chromebooks @ £300 each device -
£12,000
• 40 x dongles @ £45.00 each - £1,800
• 40 x 3 months unlimited data @ £60.00 each -
£2,400
A grant provided to Women’s Health Matters to provide staff
time to support set up of each of the 40 x devices including set
up, training, IT support and delivery to households for use by
vulnerable families working with Women’s Health Matters 40 x
£94.00 each - £3,760
Health for All - £6,270
• £8,300 funding for DIS to purchase 8 x IPADS, - smart
phones and data to enable Health for All, Breast Feeding Peer
Support service (BFPS) to increase number of women able to access
virtual support incorporating COVID 19 prevention and
management.
• 8 x Ipads @ £500 each = £4,000
• 2 x laptop @ £1,100 each = £2,200
• 2 x smart phones with data @ £35.00 each = 70.00
Equipment - £30,528
• Recharges from Children’s Services (a division of the
Council) for actual equipment purchased to include web cams, oils,
baby mats and staff training to enable virtual delivery of baby
massage courses by Children Centre staff to vulnerable families
which will include discussion on preventing and managing COVID-19 -
£30,528
Training - £15,000
• A grant of £4,000 provided to Health for All to
deliver additional Breast Feeding Peer Support training in order to
upskill and increase the number of breastfeeding peer support
volunteers by 15-20.
• A grant of £11,000 provided to Health for All to
deliver Breast Feeding Peer Support coordinator time to deliver 2
additional weekly Breastfeeding Peer Support groups.
Health for all are an existing provider who currently provide
breastfeeding peer support so are able to mobilise quickly in order
to meet this immediate work to provide support during the pandemic
therefore have the skills, knowledge and networks to implement
immediately providing a best value for money option.
As the Council would be entering into grant arrangements with the
above named organisations, the Council will have no contractual
control over enforcement of the terms. The only sanction available
with grant payments is for the Council to claw-back grant monies
unspent. However, this is balanced by the opportunity for creative
approaches to be developed making use of the flexibility of the
grant; and for added value to be obtained.
There is a risk of challenge that the grant payment is not a grant.
Legally there is some confusion about when a grant can and cannot
be used as there is a fine line between a grant (which is not
caught by the procurement rules) and a contract for services (which
is caught by the procurement rules).
Funding from which any grant payment is made must be designated as
“grant” money. If the Council wish to make a grant, the
money must be in the “grant” block. If it is not, it
can normally be moved from other blocks in the Council budget into
the grant block.
Awarding the grants to the named organisation in this way could
leave the Council open to a potential claim from other providers,
to whom this grant could be of interest, that it has not been
wholly transparent. However the risk of this would appear to be
low.
As this is a grant it is not subject to the Council’s
Contracts Procedure Rules or within the Public Contracts
Regulations 2015 but good practice and transparency will be
observed throughout.
There is no overriding legal obstacle preventing the award of the
grants and the contents of this report should be noted. In making
their final decision, the Director of Public Health should be
satisfied that the course of action chosen represents best value
for the Council.
As this decision is a consequence of a previous key decision dated
11th December 2020 (D52580) under the special urgency rule, each
separate decision at most, should be an administrative decision but
for clarity a significant operational decision for the entire
report and not be subject to call-in
Wards affected: (All Wards);
Lead officer: Janice Burberry
Decision Maker: Director of Public Health
Decision published: 28/01/2021
Effective from:
Decision:
Leeds City Council has received £10.4m,
from the Government, to support the public health response to the
COVID-19 pandemic. The funding is a one-off contribution, for the
2020-21 financial year, and is non-recurrent.
£150k of funding is to support proactive and preventative
evidence based measures, in the fight against the pandemic. As part
of this allocation, a budget has been identified for measures that
support the development of prevention projects in 6 wards with high
levels of clinical and social vulnerability as part of the Public
Health response to COVID-19:-
To provide grant funding to 3rd sector providers to deliver key
projects in the wards identified as having high levels of clinical
and social vulnerability and to provide support to communities
during the COVID-19 pandemic.
The COVID-19 pandemic has disproportionately affected older people,
those living with long term conditions and those living in more
deprived communities. As highlighted in the Marmot Review Build
Back Fairer, inequalities in social and economic conditions before
the pandemic have contributed to the high and unequal death toll.
It also highlighted the need to mitigate the impact of the pandemic
on health and health inequalities and on the social determinants of
health.
This approach to funding projects to support communities identified
by overlaying The British Red Cross vulnerability matrix with IMD
data to identify the wards with the MSOAs of most vulnerability.
This provided the list of 6 wards:
- Killingbeck and Seacroft
- Hunslet and Riverside,
- Middleton Park,
- Gipton and Harehills
- Armley
- New Farnley.
Working through strong pre-COVID-19 networks with ward members,
LCPs, Primary Care Networks, communities team, projects were
identified and have been discussed with the Proactive, Prevention
and Place (3P’s meeting). The organisations and partnerships
which will deliver the projects are all connected to local
communities and have been part of the local response to COVID-19.
These projects will meet local gaps in support for communities
where there are the highest levels of clinical and social
vulnerability.
The projects which will be delivered are listed below with an
outline of the project. The providers who will be delivering the
projects are part of local partnerships and are working closely
with the community to have identified the needs. It is essential
that Providers have experience and trust within communities in
order to deliver these programmes effectively and immediately. Many
have been working with the communities both before and during the
pandemic and have been able to identify where the gaps are but will
also identify future opportunities to engage and support
individuals, families and communities. All of the providers are
well supported by local partnership infrastructures such as LCPs,
PCNs, 1% priority neighbourhoods etc. where strong links will be
made to ensure that the projects are well co-ordinated and
supported.
Gipton and Harehills – SPACE 2 (in partnership with Zest, The
Old Fire Station, Health watch Leeds, People in Action, Shantona
Women’s and Family Centre)– grant of
£25,000
Project - We’ll Come to You - Support and Prevent
By working directly in the areas known to us to be the most hard
hit economically, physically and emotionally by the pandemic we aim
to take the Prevention message and Supportive activities out to the
community.
Using insights gathered throughout our delivery during the pandemic
we will respond to what we know to be local need, by using a van to
take staff and our volunteers (known to and trusted by the
communities of Gipton and Harehills, activity and support directly
to the streets, on a weekly basis – this will take the form
of:
- make a film "talking heads" to record local people's
feelings
- provide extra support and resources for people with learning
disabilities
- Start to use insight to start the development of a 5 year
community led recovery plan from COVID-19 to support people through
the long term effects of the pandemic.
Space 2 will manage the project, however the delivery plan is based
on a partnership approach working with organisations who delivery
other services in the ward and have a steering group established to
manage the ongoing delivery. The organisations are embedded closely
with local strategic partnerships such as the NIP and are also
delivering the COVID-19 food hub and are part of the local Connect
and Support scheme.
Killingbeck and Seacroft - LCC Communities and Environments –
grant of £15,000
Project - Health Inequalities and Digital Inclusion worker
Partnership approach working with local ward members to support the
employment of an ABCD worker. The role will identify needs or gaps
in the community and work across partners to identify solutions and
interventions. They will work closely with Social Prescribers,
third sector organisations, GP practices and local residents and
will contribute to the Leeds Outbreak Plan by offering a local
intelligence opportunity with a Seacroft lens.
The second main purpose of the role is to recruit, train and
support volunteers or Community Health Champions to work in their
communities with the aim of supporting the delivery of groups,
activities and projects that improve the health and wellbeing of
their family friends and neighbours. This funding will provide a
specific focus to being engaged with COVID-19 prevention including
the delivery of COVID-19 interventions and identifying key
community residents who can support the outbreak plan at a local
level.
Killingbeck and Seacroft - LS14 Trust – grant of
£10,000
Project - LS14 Trust - meeting the needs and engagement with local
residents and partners around the support during and after the
pandemic
Work with local volunteers and community champions to influence
local messages to support the community to access testing, engage
with the vaccination programme. Increase engagement with local
residents groups to localise key messages and make them meaningful
to residents.
Support the delivery of the vaccination programme through a
community development model, engaging and empowering the
community
Work with existing community members who are engaging with the
community hub to identify ways to support families both in relation
to prevention but also the impact of COVID-19. Develop local
community volunteers to support with COVID-19 programmes such as
vaccination rollout, testing and provide meaningful insight to
support the strategic direction of the programmes
Support families with extra support who are regularly using the hub
for support and identify opportunities to support them during and
after the pandemic.
LS14 Trust are a well-respected organisation in the local area and
are well connected to other organisations. Through their engagement
with the Boggart Hill core group, delivery of the COVID-19 Food Hub
as well as delivery of other services which support the Seacroft
community they are well known, trusted and respected. LS14 Trust
also work closely with other organisations in the area and are
closely linked to the Seacroft Local Care Partnership where their
organisation has demonstrated the impact that can be made.
Hunslet and Riverside – Hamara – grant of
£24,770
Project - Creating digital access opportunities for low income
families
Identification of digitally excluded households through attendance
at foodbank. Households invited to access digital training to
upskill and enable use of the wellbeing offer and employment
support opportunities available at Hamara. Hamara are very well
known and trusted organisation in the area with the personnel and
internal infrastructure in place to reach out to culturally diverse
families and deliver a programme requiring ongoing linkage into
other projects and support. Remote training licence procurement
will enable delivery of digital sessions. Participating households
will receive a tablet, data and be linked into the digital
training. If expressed the household may also receive vouchers to
pay for fuel.
Middleton - Belle Isle Tenant Management Organisation – grant
of £24,770
Project - Creating digital access opportunities for low income
families
Identification of digitally excluded households through tenant
management survey. Households invited to access digital training to
upskill and enable use of the wellbeing offer, TMO services and
employment support opportunities available at BITMO. Remote
training licence procurement will enable delivery of digital
sessions. Participating households will receive a tablet, data and
be linked into the digital training.
Armley, Farnley & Wortley - New Wortley Community Centre
– grant of £25,244
Project - Connecting-Armley-Connecting New Wortley
The “Connecting” model aims to utilise IPad as an asset
in the local community by providing virtual access to a wide range
of local support services. Through the partnership working with the
delivery partners this provided access to support workers from New
Wortley Community Centre, Armley Helping Hands, Barca, Leeds City
Council and other Council or third sector organisations.
Aims and objectives
The “Connecting” model aims to utilise Ipads as an
asset in the local community by providing virtual access to a wide
range of local support services. Through the partnership working
with the delivery partners this provided access to support workers
from New Wortley Community Centre, Armley Helping Hands, Barca,
Leeds City Council and other Council or third sector
organisations.
Aims
Improve digital inclusion levels in New Wortley and Armley
Reducing barriers of access
Improving confidence, skill levels and motivation around the use of
technology
Supporting local residents in accessing COVID-19 information for
approved sources
Developing relationship with local residents to engage with project
and wider local services
Objectives
Connecting individuals with those in their community through the
creation of peer support groups
Accessing benefit and housing support through Customer
Services
Accessing tailored employability support from Job shops
Engaging with individuals who have been isolated due to the impact
of COVID-19
Delivery Model
IPad will be purchased from 100% Digital Leeds, this allows for
remote access and disablement of the devices if they should be
misused or lost and is successful delivery model. Each device will
then be lent to the participant for a fixed term loan period, the
participant will meet with the NWCC support team at the Community
Centre to identify the best use of the device to create a bespoke
programme of support groups, courses, activities and information
sources. The participant will also be offered IT support to use the
device fully and develop their digital skills and improve their
confidence. At the end of the loan period, the IPad is then wiped
of any existing data and re-loaned.
As each loan period is unique to the participant, this creates a
legacy to the programme that is this beginning of their journey in
learning digital skills and developing connections with the local
community which is then replicated through each cohort. Through the
development of these community connections, we are able to build
more resilient communities and broaden the reach of public health
messaging.
The support of 100% Digital Leeds is guaranteed throughout the
project, offering both digital champion training to New Wortley
Community Centre and local volunteers in additional to 1-1 support
for all participants throughout their loan period or any subsequent
devices.
Recruitment of participants
Participants will be recruited from the local community in a number
of ways
• Engagement with New Wortley Community Centre’s
Outreach Workers
• Engagement with Armley Helping Hands , Barca, TVC, One You
Leeds
• Contact with Local Housing Officers
• Social media advertising
• Promotion from local GP’s and the social prescribing
team
Evaluation
• Tracking engagement in support groups, activities and
programmes for each participant
• Improvement in health and wellbeing through wemwebs
scoring
• Employability outcomes –moving into work or
volunteering
• Reducing in social isolation through participation in peer
to peer support groups
• Increased participating in COVID-19 testing and vaccination
due to improve access to public health messaging.
motion in the community through initial cohort of
participants
Armley, Farnley & Wortley - Armley Helping Hands & LCP
partners – grant of £10,441
Project - Listening Room
Virtual Listening Room, supporting isolated residents, linking them
to eventual face to face support, skills and exercise. Armley
Helping Hands have established a small scale test pilot of the
listening room project which has proved very successful. Armley
Helping Hands have a dedicated men’s work and adept at work
of this nature. They have excellent community links and network to
promote and engage with their target audience. The organisations is
well linked to local partnerships and had a proven record for the
delivery of projects. Consultation was undertaken in June 2020 with
older men and results highlighted the major challenged faced by the
community such as loneliness and lack of social interaction. The
listening room was developed to provide a place for men to meet in
a non-judgemental arena to discuss problems and allow for
signposting where relevant. Armley Helping Hands has been involved
in the delivery of programmes working with older men and know that
there is a high number who feel disconnected from their families,
lonely, un-employed and feeling particularly isolated and
purposeless. Many simply have no family, friends or relatives they
can talk to. We also know there is a large amount of robust peer
reviewed academic evidence of this problem in the surrounding area.
Therefore providing this space for the community to discuss issues
around COVID-19 and the impact this has on them is extremely
beneficial.
Armley Helping Hands have already evaluated the project and have
proved its worth locally. This funding allows the opportunity to
grow the project and offer this service to more men living in the
area through digital means where they do not feel comfortable to
access the centre and also currently due to lockdown
restrictions.
Delivery Model
The Delivery Model will be online using a website that will be
bespoke and designed for ease of use. The videos will initially be
live streamed in real time and then stored with links that will
allow men to access them any time they want. The listening room
will be opened from 2 days a week to 4 days and we will have a
virtual listening room which will also run out of office hours to
enable men who are working the time to access the service if they
require it. We will advertise the website using our own social
media platforms and working closely with the local GP practices and
adult services in the areas. We will also open a Facebook page and
twitter account to enable us to grow our own following.
Armley, Farnley & Wortley - TCV & Volunteers – grant
of £8,625
Project - Talking Sheds
Talking sheds will build wellbeing and develop team skills over an
8-week period. The project will consist of build a shed from
pallets on an allotment. Future “a practical group project
need on a plot” Share a communal lunch (to be COVID-19
Secure) and having a facilitated discussion (Mindful etc.) in the
afternoon.
TCV are part of local partnerships and have delivered projects in
the area and are well connected to local services and understand
the needs of the local community. The project has been developed in
response to local need with the high levels of older men who are in
need of support
Farnley and Wortley - Family Learning Team and Farnley
Children’s centre (a LCC service) – grant of
£2,400
Project - Treasure Books-Family Learning during COVID-19
Provide “first step “education engagement activities
for parents/carers whilst children centre provision remains limited
using the book Going on a Bear Hunt. Offer mental health support
activities to parents/carers. Offer opportunities for
parents/carers/children to work together to improve speaking,
listening, reading and writing.
Armley, Farnley & Wortley - TCV & Volunteers – grant
of £3,750
Project – TCV - Wildlife Walks
Responding to the need for opportunities to provide socialisation
between people who have become isolated during the pandemic. Making
use of the beneficial properties of being outdoors and taking
notice of wildlife and landscapes, taking advantage of being
outside making it easier to achieve social distancing and avoiding
infection.
Helping some build confidence to go exploring on their own or with
people they meet through the group and thus creating some enduring
benefits.
The proposal is based on past effectiveness and continuing demand
for existing groups run in other areas. Use demonstration of online
wildlife ID and walk route planning as a means to show digitally
excluded people what they are missing, and 100% Digital Leeds have
offered to drop by to do Face to Face introduction of their serve
(tablet loan etc.) to help bring some more people to digital
services where they lack device/skills/means to afford.
TCV are part of local partnerships and have delivered projects in
the area and are well connected to local services and understand
the needs of the local community. The project has been developed in
response to local need with the high levels of older men who are in
need of support
As the Council would be entering into grant arrangements with the
above named organisations, the Council will have no contractual
control over enforcement of the terms. The only sanction available
with grant payments is for the Council to claw-back grant monies
unspent. However, this is balanced by the opportunity for creative
approaches to be developed making use of the flexibility of the
grant; and for added value to be obtained.
There is a risk of challenge that the grant payment is not a grant.
Legally there is some confusion about when a grant can and cannot
be used as there is a fine line between a grant (which is not
caught by the procurement rules) and a contract for services (which
is caught by the procurement rules). The preamble to EU Procurement
Directive 2014/24/EU makes it clear at paragraph (4) that
“the mere financing, in particular through grants, of an
activity, which is frequently linked to the obligation to reimburse
the amounts received where they are not used for the purposes
intended, does not usually fall within the scope of the public
procurement rules”.
Funding from which any grant payment is made must be designated as
“grant” money. If the Council wish to make a grant, the
money must be in the “grant” block. If it is not, it
can normally be moved from other blocks in the Council budget into
the grant block.
Awarding the grants to the named organisation in this way could
leave the Council open to a potential claim from other providers,
to whom this grant could be of interest, that it has not been
wholly transparent. However the risk of this would appear to be
low.
As this is a grant it is not subject to the council’s
Contracts Procedure Rules or within the Public Contracts
Regulations 2015 but good practice and transparency will be
observed throughout.
There is no overriding legal obstacle preventing the award of the
grants and the contents of this report should be noted. In making
their final decision, the Director of Public Health should be
satisfied that the course of action chosen represents best value
for the Council.
As this decision is a consequence of a previous key decision dated
11th December 2020 (D52580) under the special urgency rule, each
separate decision at most, should be an admin decision but for
clarity a significant operational decision for the entire report
and not be subject to call-in.
Wards affected: Armley; Gipton and Harehills; Hunslet and Riverside; Killingbeck and Seacroft; Middleton Park; Various;
Lead officer: Lynne Hellewell
Decision Maker: Director of Adults and Health
Decision published: 28/01/2021
Effective from:
Decision:
The Director of Adults and Health has approved
a grant of £100,000 to Forum Central to provide additional
support for mental health over winter as set out in the attached
proposal.
Wards affected: (All Wards);
Lead officer: Carmel Langstaff
Decision Maker: Director of City Development
Decision published: 28/01/2021
Effective from:
Decision:
The Chief Officer Asset Management and
Regeneration has given approval to acquire this site on the terms
detailed in the report and attached confidential appendix.
Wards affected: Calverley and Farsley;
Lead officer: Darren Wilding
Decision Maker: Director of Resources
Decision published: 27/01/2021
Effective from:
Decision:
The Chief Digital and Information Officer
approved the waiver of contract procedure rules 8.1 and 8.2 for
intermediate value procurements to approve direct award of a
contract to Virgin Media Business (VMB) for the delivery of Managed
WAN services for 19 newly identified key sites which require a
corporate connection for a period of 6 months.
Wards affected: Various;
Lead officer: Simon Cowen
Decision Maker: Director of Resources
Decision published: 26/01/2021
Effective from:
Decision:
The Director of Resources and Housing approved
the award of a short-term contract to Whistl UK Limited for the
provision of postal goods and services for a period of one year
(from 1 February 2021 to 31 January 2022) with a contract value of
£800,000.
Wards affected: (All Wards);
Lead officer: Claudine Dawson
Decision Maker: Director of Children and Families
Decision published: 26/01/2021
Effective from:
Decision:
The Deputy Director, Children & Families
agreed the recommendation of a report relating to the placement of
a child/young person. The individual costs of the place are
£145,702.79.
It is considered in the public interest that information contained
in the report is exempt from publication as it relates to a
vulnerable child or young person of the City and the actions being
taken to enable that person to live in a safe environment.
Wards affected: Various;
Lead officer: Ruth Terry
Decision Maker: Director of Children and Families
Decision published: 26/01/2021
Effective from:
Decision:
The Deputy Director, Children & Families
agreed the recommendation of a report relating to the placement of
a child/young person. The individual costs of the place are
£111,846.43.
It is considered in the public interest that information contained
in the report is exempt from publication as it relates to a
vulnerable child or young person of the City and the actions being
taken to enable that person to live in a safe environment.
Wards affected: Various;
Lead officer: Ruth Terry
Decision Maker: Director of Children and Families
Decision published: 26/01/2021
Effective from:
Decision:
The Deputy Director, Children & Families
agreed the recommendation of a report relating to the placement of
a child/young person. The individual costs of the place are
£111,846.43.
It is considered in the public interest that information contained
in the report is exempt from publication as it relates to a
vulnerable child or young person of the City and the actions being
taken to enable that person to live in a safe environment.
Wards affected: Various;
Lead officer: Ruth Terry
Decision Maker: Director of Children and Families
Decision published: 26/01/2021
Effective from:
Decision:
The Deputy Director, Children & Families
agreed the recommendation of a report relating to the placement of
a child/young person. The individual costs of the place are
£208,571.43.
It is considered in the public interest that information contained
in the report is exempt from publication as it relates to a
vulnerable child or young person of the City and the actions being
taken to enable that person to live in a safe environment.
Wards affected: Various;
Lead officer: Ruth Terry
Decision Maker: Director of Children and Families
Decision published: 26/01/2021
Effective from:
Decision:
The Deputy Director, Children & Families
agreed the recommendation of a report relating to the placement of
a child/young person. The individual costs of the place are
£264,706.34.
It is considered in the public interest that information contained
in the report is exempt from publication as it relates to a
vulnerable child or young person of the City and the actions being
taken to enable that person to live in a safe environment.
Wards affected: Various;
Lead officer: Ruth Terry
Decision Maker: Director of Children and Families
Decision published: 26/01/2021
Effective from:
Decision:
The Deputy Director, Children & Families
agreed the recommendation of a report relating to the placement of
a child/young person. The individual costs of the place are
£272,679.51.
It is considered in the public interest that information contained
in the report is exempt from publication as it relates to a
vulnerable child or young person of the City and the actions being
taken to enable that person to live in a safe environment.
Wards affected: Various;
Lead officer: Ruth Terry
Decision Maker: Director of Children and Families
Decision published: 26/01/2021
Effective from:
Decision:
The Deputy Director, Children & Families
agreed the recommendation of a report relating to the placement of
a child/young person. The individual costs of the place are
£247,678.57.
It is considered in the public interest that information contained
in the report is exempt from publication as it relates to a
vulnerable child or young person of the City and the actions being
taken to enable that person to live in a safe environment.
Wards affected: Various;
Lead officer: Ruth Terry
Decision Maker: Director of Children and Families
Decision published: 26/01/2021
Effective from:
Decision:
The Deputy Director, Children & Families
agreed the recommendation of a report relating to the placement of
a child/young person. The individual costs of the place are
£186,410.71.
It is considered in the public interest that information contained
in the report is exempt from publication as it relates to a
vulnerable child or young person of the City and the actions being
taken to enable that person to live in a safe environment.
Wards affected: Various;
Lead officer: Ruth Terry
Decision Maker: Director of Children and Families
Decision published: 26/01/2021
Effective from:
Decision:
The Deputy Director, Children & Families
agreed the recommendation of a report relating to the placement of
a child/young person. The individual costs of the place are
£169,933.57.
It is considered in the public interest that information contained
in the report is exempt from publication as it relates to a
vulnerable child or young person of the City and the actions being
taken to enable that person to live in a safe environment.
Wards affected: Various;
Lead officer: Ruth Terry
Decision Maker: Director of City Development
Decision published: 25/01/2021
Effective from:
Decision:
The Chief Planning Officer has re-designated
the Hyde Park Neighbourhood Forum.
Wards affected: Headingley and Hyde Park; Little London and Woodhouse;
Lead officer: Caroline Harris
Decision Maker: Director of Public Health
Decision published: 25/01/2021
Effective from:
Decision:
Leeds City Council has received £10.4m,
from the Government, to support the public health response to the
COVID-19 pandemic. The funding is a one-off contribution, for the
2020-21 financial year, and is non-recurrent.
This funding is to support proactive and preventative evidence
based measures, in the fight against the pandemic, which are
informed by the Leeds outbreak plan. Setting up a local contact
tracing service is a requirement of central Government. As part of
this allocation, a budget has been identified for this local
contact tracing service, it is necessary that this service is
implemented immediately as part of the Public Health response to
COVID-19:-
The development and implementation of the local contact tracing
service for Leeds was launched in November 2020. This service has
been developed at pace with partners across the Council.
The programmes developed are detailed below, it is anticipated
costs for 12 months from November 2020 – December 2021 will
be approximately £785,158. There will be flexibility with
this approach depending on the specific needs of the Leeds
population and the rates of infection, therefore costs may increase
or decrease in line with local data.
Wards affected: (All Wards);
Lead officer: Sharon Foster
Decision Maker: Director of Resources
Decision published: 25/01/2021
Effective from: 21/01/2021
Decision:
In line with Contract Procedure Rule (CPR) 18,
the Director of Resources & Housing approved the request to
appoint Restore Digital Ltd to the Framework Agreement to Restore
Digital Ltd for the provision of Scanning and Document Digitisation
Services for a period of four (4) years from 1st February 2021 to
31st January 2025. The total spend allowable under the Framework
Agreement is £2 million.
Wards affected: (All Wards);
Lead officer: Lorna Gladstone
To inject into the capital programme and approve the spending of £5,542,873 pothole grant funding in accordance with the requirements of the Department for Transport.
Decision Maker: Director of City Development
Decision published: 21/01/2021
Effective from: 06/02/2021
Decision:
The Chief Officer (Highways and Transportation) :
a) Approved the injection of £5,542,873 into the Capital Programme funded from the DfT Pothole capital grant 2020/21.
b) Gave authority to incur expenditure of £5,542,873 on carriageway maintenance, to repair potholes and prevent potholes forming. This will be made up of £4,819,889 works costs and £722,984 fees, funded from Government Grant, as detailed in Appendix A.
Wards affected: (All Wards);
Lead officer: Richard Hobson
Leeds City Council have been awarded a grant from Public Health England after a successful bid to the Rough Sleeping Grant Programme. The grant is to establish a drug and alcohol street based lifestyle team to provide specialist support to people rough sleeping and recovering from rough sleeping.
Approval is being sought to award a grant to Humankind to set up and deliver the project as part of the Forward Leeds drug and alcohol service.
This is a key decision as expenditure is over £500,000 and is to be awarded as a grant. The grant is being provided by Public Health England from their Rough Sleeping Grant.
Decision Maker: Director of Public Health
Decision published: 20/01/2021
Effective from: 05/02/2021
Decision:
The Director of Public Health :
Wards affected: (All Wards);
Lead officer: Barry Ibbetson, Ian Street
Leeds City Council has submitted a bid to Public Health England/ Department of Health and Social Care for the Out of Hospital Care – Shared Outcomes Fund. The purpose of the fund is to assist timely discharge from hospital and prevent hospital admittance where possible, for people who are rough sleeping or at risk of rough sleeping. A bid has been submitted for £640k to spend on a range of activities up to the end of March 2021.
We are awaiting notification of whether the bid has been successful. It is anticipated that if the grant is approved, an immediate start will be required. Approval is required to accept the grant and to progress the activities outlined in the bid. The bid includes activity within the Council, with the Clinical Commissioning Group and health partners.
This is a key decision as expenditure is anticipated to be over £500,000 and is to be awarded as a grant. The grant if awarded will be provided by Public Health England/ Department of Health and Social Care for the Out of Hospital Care – Shared Outcomes Fund.
Decision Maker: Director of Adults and Health
Decision published: 20/01/2021
Effective from: 05/02/2021
Decision:
The Director of Adults and Health :-
Wards affected: (All Wards);
Lead officer: Julie Staton
Authority to undertake a procurement exercise to commission a five year contract with the option to extend for a period of up to 36 months for the provision of a Personal Assistant (PA), Managed Bank Account (MBA) and Payroll Service for people in receipt of a Direct Payment of Personal Health Budget
Decision Maker: Director of Adults and Health
Decision published: 20/01/2021
Effective from: 05/02/2021
Decision:
The Director of Adults and Health :
Noted that:
· The Director of Adults and Health will use her delegated authority to take commissioning decisions which will be a direct consequence of this key decision, for example approval of the detailed specifications for procurement and subsequent contract award. This is subject to the decision being in line with the key principles and features as described in the report.
Wards affected: (All Wards);
Lead officer: Caroline Baria